The board has an owner of its structure, and its milestones are capped versions
Context
The verification of each iteration asks whether a branch is correct. It does not ask whether the branch was worth building. It does not ask whether the branch belonged to the plan, or whether the plan is still the work. One iteration at a time, these three questions are not visible. Across ten iterations, the answers are clear. An agent in the middle of a run has every reason to find the next thing to build. So it cannot also weigh that thing against the plan.
Five failures on this board show the gap. Nothing in them was bad work. Each was good work that entered the board with no comparison against other good work.
The reader failure. On 2026-08-15 this repository filed 45 issues and closed 16. Of the new issues, 23 were findings from a run of the engine over its own corpus. Every one was real, and none had a reader outside this repository. Nobody compared any of them against the tutorial, the install path or the first adopter, which were open the whole time.
The plan failure. Over 2026-08-12 and 2026-08-13, 41 issues closed, and every one carried a milestone. From 2026-08-15 to 2026-08-17, 33 issues closed, and 28 of them carried none. So 85% of three days of work sat outside the plan. In those days, M5, M6, M7 and the library track stood still. The value rule caught the reader half: 22 of those closes carried the self-audit label. Nothing measured the other half.
The intake failure. The value rule already kept work with no outside reader off the tracker. But the rule acted at the top of a run and at every fifth merge, and a run files an issue at neither moment. Over the 30 days to 2026-09-20, the board opened 279 issues and closed 259, so the open count did not move. Of the 28 issues with no milestone, 21 were ten days old or less.
The bookkeeping failure. On 2026-08-20, four of the eight milestones, M1 to M4, held zero open issues and were still open. The build order had a policy to close an epic and none to close the milestone around it. A board that shows eight milestones in progress, when four are finished, tells a reader that the plan has barely started.
The single-issue failure. On the same day, one issue, #73, held M5 open. Its skills and its maintainer agent were on disk. Its only open half was a measurement that answered to the bar of M7. So one misfiled issue held a milestone open and moved the selection order past it to M6 and M7.
The milestones themselves were part of the cause. The M-sequence was a bootstrap plan: it named what the system must do, in the order that the parts depend on each other. Its themes had no end that a release could name and no date, so none of the later ones closed. Version 0.1 shipped on 2026-09-07.
Decision
One agent owns the structure of the board, and never its scope. Structure is where work sits and how urgent it is: milestones, milestone membership, folds, the bug and adopter-blocking labels, and the paid-experiment label (HW-PD-0025). Scope is what the work is and when it is done, and scope stays with the owner. The agent is headwater-product-owner. It runs outside the context of any builder. It runs standalone, at the top of a run, at every fifth merge and at the end of a run. It names every write with its reason, in a form that the owner can reverse.
No agent of a run files an issue, the parent included, and only the product owner files one. A stage or the parent writes a finding that is not the issue in hand as one line in the intake file of the run. The product owner rules on each line with one of five rulings: apply, fold, record, admit or backlog. Apply was added on 2026-10-13 by #1483. It sends a one-line remedy to one pull request at the end of the run. So the comparison against other work occurs before the filing, and not after it.
Every open milestone is a version. The owner moved the board to version milestones on 2026-09-20. M7, M8 and M9 closed, and their open issues moved forward. R1 took the name 0.1, and M6b took the name 0.7 with its bar unchanged. The library track and the ecosystem track became track: labels over the backlog. Neither has an end that a release can name.
A version milestone is a statement, a cap and a date. The statement is one sentence about what an adopter can do after the release that they could not do before. The cap is 15 open issues. The date is the owner's. An issue enters a version only when the statement is false without it. Other real work carries no milestone, and that is the backlog. The versions are worked in numeric order.
The product owner writes questions, and the owner answers them. Each decision that the owner owes becomes one RULING block with a recommended answer and a defer option. The agent that dispatched the product owner puts the blocks to the owner.
Consequences
.claude/agents/headwater-product-owner.md carries the rules that the agent obeys, and this record carries the evidence for them. The five failures map to the five parts of its report. Part 1 reports the share of closes with no milestone, which is the number that would have shown the plan failure while it occurred. Part 2 closes a finished milestone. Part 3 finds a misfiled issue.
A closed version milestone is a release that the owner has not cut. The product owner reports it first, and only the owner starts a release. No agent pushes a tag.
A cap that only grows is not a cap. So an admission into a full version names the issue that it moves to the backlog.
Added 2026-10-02: a version milestone is decoupled. The product owner first proposed the editor work as two milestones. One held the VS Code and JetBrains features, the store listings and the browsing panel. The other held the engine requirement, the release index, the downloads and three new platforms. Neither could close before its slowest part. In four rulings that day, the owner split the work by client, by platform, and by core against optional surface. The owner also put the shared engine requirement ahead of all of it. The result was six milestones of 1 to 13 issues each. Each split also moved clauses between issues: #1613 took the JetBrains half of #1594, #1575 and #1609, and #1610 took the JetBrains half of #1600. One issue that moved later, #1601, still carried adopter-blocking, which would have put it ahead of every milestone. The owner then asked whether the issues link to each other, so that a reorder shows its effect. Their bodies named each dependency in prose, and no issue carried a GitHub blocked by link. The owner ruled that the link is preferred. The agent's section Decoupling a milestone states the test that these rulings applied.
This record does not give the product owner scope. It does not close an issue as done, and it does not edit a Done-when clause or a bar. A version statement that the owner has not accepted is a proposal. A window where the intake rulings admit more than they fold and record is a finding against this decision. The report states it.